Project Timeline
- December 1 –January 8 Shift of bound periodicals and shelving on 6th floor
-
December 28 – January 12 Movers in Central and Divinity Libraries!
Bound periodicals (6th floor) to Library Annex
Government documents (4th floor) to Library Annex
Payne Room (6th floor) and Divinity Microforms to Library Annex
-
January 12 – January 18 Completion of book shift from 8th floor to 6th floor
Removal of bookshelves on 8th floor
-
January 18–29 Deconstruction of 8th floor (21st Avenue side)
-
February 1—May 14 Construction of new public space on 8th floor
-
May-December 2010 Possible additional projects, including community room and café
|